Holacracy Community of Practice Archive, 2015-2019 Community Holacracy Web Site

Tactical meetings - 'no update' project updates

As circle lead link, I wondered what (if any) is acceptable tolerance for project updates that consist of 'no update'. We're new to Holacracy and are dealing with projects that span the transition and aren't always perfectly aligned to new roles.

Do I have authority to ask / expect for more detail & progress from week to week?

Thanks,

Leo

 

 

 

3 Replies
LiuYan@HK
06/15/2016

We had the experience that some projects do not have update for quite a while. 

Then we just suggest to put those projects on hold - so that we don't ask about it every time. Then if it stays so for long, then we examine if that is still aligned with our strategy, if not, then we abandon that project. 

Based on what I know, in Holacracy, we cannot really tell people how to do things or give deadlines - it's up for the person to manage their work and priority.  So if a project should have updates but is not having it, then someone is bound to have tension, and can raise it at Tac meeting to propose a next action/project related. 

 

Kevin
06/16/2016

Leo,

My advice is that you should model Holacratic behaviors to support the power shift your organization is trying to achieve, but that does not limit your ability to get updates and drive action on the project.  Here are some of the tools available to you as lead link:

1.  Like any circle member, lean on the duties found in Article 4.  In particular, 4.1.1(b) and (c) should be really useful.  Ask the person what other projects are prioritized of the one that is not receiving attention.  Ask the person when he or she expects to have it done.

2.  Also, remember that each project should have a next-action associated with it.  Ask what the next-action is on that project.  If there is one, you will be able to help evaluate whether that action is going to move the project forward and is truly the next step to take or whether there is some intermediate action that should be included.  If there is not one, ask the person to define a next-action.  This will reinforce the best practices of Getting Things Done and allow the role-filler to come into compliance with his/her responsibilities as outlined in Article 1.  See especially 1.2 . . . does the person have a trusted system (1.2.4) and is he/she defining next-actions (1.2.3) effectively?  This step is also available not just to the lead link but to any circle member.

3.  As lead link, you are accountable for the priorities of the circle.  If you think the neglected project is more important and needs to be elevated in priority, you can say so.  This is ideally done in a collaborative way and with an understanding of the other projects and priorities, but ultimately, you can direct the resources (including employee time) toward the priorities that you think are most deserving.

Hope these ideas help get you started.  To answer your final question, I don't think you as LL can expect any particular project to move at any particular pace unless you have received some any indication to that effect using the tools above or unless common sense would make it obvious that it should have moved at that pace (i.e. estimated tax payment due on June 15 either makes the deadline or doesn't).  However, you always have the authority to ask for more detail, ideally framed as above, and to drive action using your role's authority and your rights as a member of the circle.

Kevin

leo white
06/20/2016

Thanks Kevin,

That's a great clarification and advice. 

Cheers,
Leo